Pembangunan Saluran Air di Jl Nusa Indah I Capai 98,9 Persen

Channel Construction on Jl. Nusa Indah I is Almost Complete

Construction of 632-meter channel on Jl. Nusa Indah I, Malaka Jaya, Duren Sawit, East Jakarta is almost complete since it has currently reached 98.9 percent.

Construction progress has reached 98.9 percent

East Jakarta Water Resources (SDA) Sub-agency's Development and Drainage Improvement Section Head, Tengku Saugi Zikri conveyed, this water channel was installed using concreted U-Ditch and Box Culvert.

His side used U-Ditch with size 80x80 centimeters along 409 meters and size 100x100 centimeters along 70 meters.

Ancol SDA Unit Dredges Channel on Jl. Tongkol

Meanwhile for Box Culvert, his side used size 80x80 centimeters along 16 meters and size 100x100 centimeters along 5 meters. Then continued with size 150x150 centimeters along 132 meters.

"Construction progress has reached 98.9 percent," he said, Wednesday (12/9).

This channel which located in Perumnas Klender Public Housing is expected to hold water from Nusa Indah Connecting (Phb) Channel and drain it into I Gusti Ngurah Rai Channel.

"Hopefully, this channel can be used to minimize inundation and flooding," he asserted.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2618 personNurito
  2. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye955 personFolmer
  3. PSEL Project to Solve Jakarta's Waste Crisis, Says Pramono

    access_time06-05-2026 remove_red_eye913 personDessy Suciati
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye811 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye720 personBudhi Firmansyah Surapati